Live Machine Map
Every track machine in today's Daily Progress, plotted on actual RDPS-surveyed track geometry across all three divisions • colour = division, ring = Tamping/Non-Tamping, number = machines at that spot • click a pin for full detail
Jump to a division
Jump closer — by Sr. DEN jurisdiction
By Machine Type — Target vs Progress, with Year-on-Year
Pick any of the 16 machine types for its own Target-vs-Progress chart and comparison to the same period last year • GM-presentation ready
Cumulative Progress — by Machine Type
Actual vs pro-rata target, FY 2026-27 to date, against each type's own annual target • click a bar for the machines of that type • figures shown per unit of measure (Km/R-S/T-O/Unit) — fleet-wide totals are a breakdown since types mix units
Year-on-Year
Cumulative progress, same period • click a bar for that type's year-on-year detail • figures shown per unit of measure (Km/R-S/T-O/Unit) — fleet-wide totals are a breakdown since types mix units
Machine-wise Shortfall & Availability
From the separate “Shortfall Reasons” Google Sheet — division-wise availability, FY-to-date down-days per machine, and fleet utilisation • data as of —
Availability by Division
Click a division for its machines • “Construction Line” = machines on new-line construction ahead of commissioning
Machine-wise Shortfall Breakdown
Pick a machine type for its own down-day reason breakdown, with that type's utilisation figures shown alongside • click a bar (or a machine card) for its full detail
Sr.DEN Alert Message
Auto-drafted from today's Exception Sheet — names every machine and its specific issue, longest-pending first — edit and copy/WhatsApp as-is
Exceptions
Linear summary, colour-coded by type, with start date • click any card for full remarks
Failure / Under Repair
Under IOH/POH
Under Commissioning
Block / Line-Clear Not Availed
Under Maintenance
Under Movement / Transit
Other / Uncategorised
Open Exceptions by Category
— • click a bar for the machines
Fleet Health — IOH/POH Release, FY 2026-27
Primary source: IOH/POH Planning's own “Progress 2026-27” sheet (parent division, who's arrived, who's completed) • not the Exception Sheet or Cumulative Progress Status. The current-FY schedule above, the all-fleet multi-year outlook (FY 27-30), and CPOH/RYP's own forward POH planning for FY 27-30 are all below, on this tab.
Fleet Age Distribution
SWR track machine fleet • click a bar for the machine list
Division-wise — FY 2026-27 Schedule
Click a division to present it separately — bulleted, with a Sr.DEN breakdown, ready to show on-site
Multi-Year IOH/POH Outlook — FY 2027-28 to 2029-30
Strictly from the IOH POH Details 27-30 workbook, every SWR machine • click a division for the year-by-year breakdown
CPOH/RYP — Central POH Planning, FY 2027-28 to 2029-30
Dy.CE/TM's own forward proposal to Dy.CE/CPOH/RYP • the current year's CPOH/RYP release status is in the “Division-wise FY 2026-27 Schedule” card above
Proposed for POH — FY 2027-28
Firm proposal with engine-hours, governing reason and probable sparing month • click a row for full detail
| Machine | Last POH | EH Since Last POH | Governing Reason | Probable Sparing |
|---|
Tentative — FY 2028-29
Lighter detail, still provisional
| Machine | Type | Last POH |
|---|
Tentative — FY 2029-30
Lighter detail, still provisional
| Machine | Type | Last POH Details |
|---|
Tamping Unit Demand
Which tamping unit each machine will need, and when • same letter, FY 2027-28 & 2028-29
| For FY | Tamping Type | Machine | Month | Make |
|---|
Sr.DEN Alert — Double-Shift Fatigue
Auto-drafted for jurisdictions with a >12h shift on record
Double-Shift Progress by Machine
Days worked in double shift • click a bar for the shift-by-shift log
Shifts Exceeding 12 Hours — Staff Health Flag
Maintenance-started to back-at-siding duration • auto-messaged to the concerned Sr.DEN
Full Shift Log
| Date | Machine | Div | Sr.DEN | Shift | Maint. Started | Readiness | Back at Siding | Duration (h) | Progress |
|---|
53-Point Track Machine Action Plan — 15-Day Review
A standing, board-level action plan across Safety, Reliability, Quality, Availability, Expenditure, Staff Welfare, Skill Development and Miscellaneous • refreshed with a new review column roughly every 15 days
Points by Category
Click a bar to filter the list below to that category
Supervisor Load
Action points per nominated supervisor this cycle
All 53 Action Points
Latest review shown on each card • click a card for the full history since April
Unit Cost & Daily Cost — by Machine
What each machine actually costs SWR: Daily Cost (Rs/day, incurred whether the machine works or not) and Unit Cost (Rs per unit of progress — Rs/Km, Rs/T-O etc, per that machine's own progress unit) • factual snapshot from the Unit Cost workbooks
Financial Year
Click a year — every chart, KPI and the table below follow it
Cost by Machine Type
Pick a machine type (group) to break both charts below into one bar per individual machine, with that group's total cost shown here • leave blank for the type-average view
Unit Cost by Machine Type
Average Rs per unit of progress, by type • click a bar to see every machine of that type
Daily Cost by Machine Type
Average Rs/day (incurred regardless of output), by type • click a bar to see every machine of that type
Machine-wise Unit Cost & Daily Cost
Every machine in the source sheet • click a row for the full cost breakdown
| Machine | Type | Division | Unit | Daily Cost | Unit Cost | YoY Δ |
|---|
Infrastructure Planning — TM Sidings & Rest Houses
Sidings, Rest Houses & Satellite Depots — Map
Every surveyed station with a TM siding / rest-house / satellite-depot entry • colour = division, symbol = feature, ring = status • click a marker for full detail
Sr.DEN — wise Breakdown
Every Sr.DEN jurisdiction across all three divisions • click a row for its stations
| Sr.DEN | Division | Stations | Siding Avail. | Siding Sanc. | Siding Prop. | RH Avail. | RH Pending |
|---|
By Division
Click a division for its full station-level breakdown, including sanctioned-siding/rest-house execution position
FY Siding Target — by Division
Click a bar for the division's target detail
Pending — Responsibility / Status
Who the pending cases sit with: Construction Organisation (CN), Division (IRPSM), Gati Shakti, or Not Feasible • click a slice for the stations
Contract Runway
Every agreement's full life — LOA issue to currency date — on one timeline • click a bar for full agreement detail
Expired, no renewal yet
Expired, renewal in pipeline
Expiring within 90 days
Valid
Today
By Pipeline Stage
Click a stage for its list of indents
Live Data Sources
Six Supabase-synced Google Sheets that the live pipeline now fetches but that don't yet have a purpose-built dashboard view of their own — this tab gives each one an honest first look exactly as the pipeline hands it over, ahead of a future dedicated redesign for any of them
Cumulative Failures for TMC Record
Year-by-year cumulative failure data from the “CUMULATIVE FAILURES FOR TMC RECORD” Google Sheet, one entry per financial year
Daily Machine Positions
Each machine's current “Stabled At” location, from the live Daily Positions Google Sheet • a simpler, complementary view to the SWR Network Map tab (which plots positions on real track geometry) — not a replacement for it, and not the same underlying source
HQ Summary Items
Fleet-by-type holding and progress summary from the “HQ Summary Items” Google Sheet
Monthly Machine
Per-category, per-period progress from the “Monthly Machine” Google Sheet
RDPS Track Survey Points
Static RDPS track-survey reference data (route, km-chainage, GPS position and nearby station) grouped by division — a reference/lookup table, not a day-to-day operational feed
Fleet Availability & Utilisation
Division-wise availability and fleet-utilisation figures from a separate Google Sheet — despite the similar name, this is not the Daily-Progress shortfall-category log that the “Reason for Shortfall” tab already covers